A and B can do a work in 10 days. B and C can do the same work in 15 days. C and A can complete the same work in 20 days. In how many days can C alone complete the work ?

1
120 days
2
118 days
3
115 days
4
110 days
Question Details
Time to Solve: 12
Exam: HTET
Level/Paper: Level 1
Chapter: Word Problems
Topic: Time & Work
Correct Answer
Option A
Explanation

To determine how many days C alone can complete the work, we need to analyze the given information and use it to find the individual work rates of A, B, and C. 1. Combined Work Rates: - A and B together can complete the work in 10 days. Therefore, their combined work rate is \( \frac{1}{10} \) of the work per day. - B and C together can complete the…Read More