Easy

A can complete a particular task in 20 days whereas B can complete that task in 10 days. Both worked together for 4 days and then B leaves the task, then how many days will A take to complete the remaining task ?

1
12 Days
2
4 days
3
6 days
4
8 days
Question Details
Time to Solve: 12
Exam: HTET
Level/Paper: Level 1
Chapter: Word Problems
Topic: Time & Work
Correct Answer
Option D
Explanation

To determine how many days A will take to complete the remaining task after B leaves, we need to follow these steps: 1. Calculate the work done by A and B together in 4 days: - A's rate of work is 1/20 of the task per day. - B's rate of work is 1/10 of the task per day. - Together, A and B can complete (1/20 + 1/10) of…Read More