Question
Easy

Which of the following is not a phase or activity of requirement engineering in context of software engineering?

1
Feasibility study
2
Requirements elicitation and analysis
3
Requirement validation
4
Component specification
Question Details
Time to Solve: 12
Exam: HTET
Level/Paper: Level 3
Chapter: Software Engineering & Problem Solving
Topic: SDLC (Major stages)
Correct Answer
Option D
Explanation

The correct option is (4): Component specification falls outside the boundary of the core requirements engineering (RE) process. Requirements Engineering is exclusively focused on establishing what the system must do by defining its services and operating constraints. Component specification, which involves the detailed design, structure, and interfaces of individual software modules or subsystems, is an activity that takes place during the subsequent Software Design phase of the Software Development Life…Read More