Question
Easy
A project is worthwhile or profitable if its Net Present Value (NPV) is:
1
less than 0
2
greater than 0
3
equal to 0
4
greater than 1
Question Details
Time to Solve: 12
Exam: HTET
Level/Paper: Level 3
Chapter: Business Finance and Marketing
Topic: Business Finance
Correct Answer
Option B
Explanation
The correct option is 2: Net Present Value (NPV) is a primary capital budgeting technique that determines a project's profitability by discounting all expected future cash flows back to their present value and subtracting the initial investment. A project is considered worthwhile, profitable, or value-adding if its NPV is greater than 0 (positive). This positive value signifies that the project's cash inflows, after being discounted by the firm's required rateтАжRead More
Similar Questions from REET Exam - Paper 1 - Year 2018
Question 1
Easy
Source :
HTET 2018
The budget that is prepared first of all is:
Chapter :
Business Finance and Marketing
Topic :
Business Finance
Question 2
Easy
Source :
HTET 2018
A company earned a profit of Rs. 30,000 during the year 2014-15. If the marginal cost and selling price of a product are Rs. 8тАж
Chapter :
Business Finance and Marketing
Topic :
Business Finance
Question 3
Easy
Source :
HTET 2018
Which among the following is an example of capital expenditure?
Chapter :
Business Finance and Marketing
Topic :
Business Finance
Question 4
Easy
Source :
HTET 2018
Writing off lost capital is one of the ways in which the share capital can be :
Chapter :
Business Finance and Marketing
Topic :
Business Finance