If 12 men do a piece of work in 20 days, then in how many days will 60 men do the same work?

1
4
2
3
3
2
4
6
Question Details
Time to Solve: 12
Exam: HTET
Level/Paper: Level 2
Chapter: Word Problems
Topic: Time & Work
Correct Answer
Option A
Explanation

To determine how many days it will take for 60 men to complete the same piece of work that 12 men can complete in 20 days, we can use the concept of man-days, which is a measure of the total amount of work done. 1. Calculate the total amount of work in man-days: - If 12 men can complete the work in 20 days, the total work is calculated as:тАжRead More